First zinc and lead concentrate from South32’s Taylor project delayed to H1 2028

South32 said on April 30 that first production from its 4.3-million-tonne-per-year Taylor zinc-lead-silver project in Arizona has been delayed to the first half of the 2028 calendar year, with steady-state output of approximately 123,000 tonnes per year of payable zinc and 155,000 tonnes per year of payable lead now expected by June 2031.

Key takeaways:

  • Execution setbacks persist: First production delayed to H1 2028 and costs rising, reflecting contractor and construction challenges.
  • Output trimmed, but scale intact: Lower annual volumes and grades offset by larger reserves and a ~33-year mine life.
  • Copper adds upside optionality: Expanded Peake resource offers future multi-metal potential, but timing remains unclear.

Hermosa project timeline delays and revised ramp-up

First production from Taylor — the first development at South32’s broader Hermosa project — has been pushed back by approximately a year from the previous guidance of the first half of 2027, the company said.

Nameplate processing capacity of 4.3 million tpy is expected by June 2031, delayed from June 2030.

Annual steady-state output is expected to average 123,000 tpy of payable zinc, 155,000 tpy of payable lead, and 8.2 million ounces per year of silver, down by 6.8%, 4.9% and 3.5% respectively. South32’s feasibility study guidance estimated 132,000 tonnes of zinc, 163,000 tonnes of lead, and 8.5 million ounces of silver.

Total payable production over the project’s initial operating life is expected to reach 3.7 million tonnes of zinc, 4.6 million tonnes of lead and 247 million ounces of silver.

Operational challenges and mitigation efforts

The delays are due to contractor underperformance, as well as engineering and procurement delays on shaft sinking. The company said intervention measures — including strengthening contractor leadership, engaging specialist performance advisers and bringing critical scope under direct owner management — had only partially offset the impact.

“First production is expected in [the first half of 2028] and nameplate capacity by [June 2031], reflecting our revised expectation for shaft construction, due to contractor performance and productivity challenges,” South32 chief executive officer Graham Kerr said.

Fastmarkets’ twice-monthly assessment of the zinc spot concentrate TC, cif China, was $(20)-5 per tonne on April 24, down from $(15)-15 per tonne on April 10.

Future copper output at Hermosa

The project update also flagged future copper output potential at Hermosa via the adjacent Peake deposit.

South32 said the mineral resource estimate for Peake was increased by 32% to 33 million tonnes at 0.87% copper, 0.28% zinc, 0.32% lead and 36 grams per tonne of silver. The previous estimate, dated June 30, 2025, was 25 million tonnes at 0.79% copper.

The entire Peake resource remains classified as inferred – the lowest confidence category under the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC) code.

The Taylor process plant has been designed with flexibility to allow for the addition of “a low-cost copper circuit… from Peake and Taylor Deeps,” South32 said.

Total metallurgical recovery assumptions disclosed for Peake are 73% for copper, 75% for zinc and 85% for lead, with silver recovery of 52% to the lead concentrate and 30% to the copper concentrate.

South32 has not disclosed a development timeline for Peake beyond “medium to longer term.”

Mine life extended up to 33 years

Taylor’s initial operating life was extended by approximately five years to about 33 years.

The ore reserve estimate was raised by 52% to 99 million tonnes at 3.95% zinc, 4.50% lead and 77 grams per tonne silver, compared with the previous estimate dated June 30, 2025, of 65 million tonnes at 4.35% zinc, 4.90% lead and 82 grams per tonne silver. The reserve underpins approximately 25 years of the operating life, South32 said.

Mined ore grades over the life of the operation are expected to average 3.7% zinc, 4.1% lead and 76 grams per tonne of silver, marginally below the feasibility study guidance of 3.9% zinc, 4.3% lead and 78 grams per tonne of silver. South32 said the larger volume of ore offset the slightly lower average metal grades.

Operating costs have been revised to approximately US$100 per tonne of ore processed, up from approximately US$86 per tonne at the feasibility study, reflecting general inflation and higher assumed energy costs, the company said.

FAST-41 critical infrastructure permitting process

Hermosa was the first mining project added to the US government’s FAST-41 critical infrastructure permitting process. South32 said federal permitting under FAST-41 was progressing on schedule, with a final record of decision and notice to proceed on track for the second half of 2026. All state approvals required to construct Taylor have been granted.

Taylor concentrates will be transported by road from the site to the port of Guaymas in Sonora, Mexico, or to Corpus Christi, Texas, for export, South32 said.

Fastmarkets assessed the lead spot concentrate TC, high silver, cif China at $(280)-(200) per tonne on April 24, up from $(280)-(220) per tonne a month earlier.

Fastmarkets assessed the lead spot concentrate TC, low silver, cif China at $(200)-(160) per tonne on April 24, also up from $(210)-(180) per tonne a month earlier.

Fastmarkets calculated the weekly copper concentrates TC index, cif Asia Pacific – the midpoint between smelter and trader buying levels – at $(115.10) per tonne on Friday May 1, down by $7.80 per tonne from $(107.30) per tonne a week earlier.

Want to learn more about what is happening at the cutting-edge of critical minerals and battery raw materials? Listen to our Fast Forward podcast series for insight, debate and news from the major players.

What to read next
JX Advanced Metals, Mitsui Kinzoku, Marubeni and Mitsubishi Materials(MMC) inked a deal to integrate MMC's copper concentrate procurement and related products sales business into Pan Pacific Copper (PPC), marking a significant consolidation of Japan's copper concentrate purchasing sector amid persistent pressure from weak treatment and refining charges (TC/RCs).
An interview with Assistant Secretary, Michael Cadenazzi at the Department of War, as it is known, and Zach Boykin, the department's technical director for strategic and critical minerals with Andrea Hotter for the Fast Forward podcast.
Critical minerals have long sat quietly in the background of industrial supply chains. Today, they are at the centre of national security strategy. Fastmarkets’ Andrea Hotter speaks to senior officials from the US Department of Defense in the lastest Fast Forward podcast episode.
The recent appreciation of the Chinese yuan against the US dollar is rippling through Asia’s ferrosilicon market, squeezing Chinese export margins, lifting regional prices and shifting currency risks downstream to buyers.
Copper producers, including Atlas Mining, reported higher earnings in the first quarter of 2026 on the back of elevated copper prices, while concentrate output declined at several operations in Chile, Brazil, Colombia and the Philippines due to lower ore grades and disruptions, according to company results reviewed by Fastmarkets.
The US company EVelution Energy outlined its plans to produce 3,000 tonnes per year of cobalt metal in the United States from Congolese hydroxide, speaking with Fastmarkets on Wednesday May 13 on the sidelines of the Cobalt Congress that took place in Madrid, Spain (May 12-13).