Newcrest declares force majeure on Cadia contracts following dam breach

Newcrest Mining Ltd has declared force majeure on contracts for copper concentrates supply from its Cadia mine, where operations have been shut since March 10 due to a collapsed tailings dam.

The Australian company sent notifications to customers on Wednesday March 14 that it could not guarantee contractual supply of copper concentrates, two sources, who declined to be named, said.

A spokesman for Newcrest declined to comment, while referring to a statement made on Monday indicating that 2018 guidance would be adversely affected. 

Newmont is in the process of reviewing its tailings facility at Cadia in New South Wales, Australia, where a tailings pool dam collapsed on Friday March 9, and is looking at possible alternative locations to store mining residues.

Cadia produced 63,805 tonnes of copper in concentrate in 2017. The immediate effect on the copper concentrates market and spot treatment and refining charges (TC/RCs) is as yet unclear, sources said.

“It remains a question in the market as to how long Cadia will be out, but we’re not expecting a long absence,” one source said.

“Some smelters have nearby shipments due from Cadia and if the force majeure lasts a long time, there will be an impact [on the market],” a second source said.

Copper concentrate TC/RCs fell in the first quarter of 2018 as the market priced in potential mine disruptions from labour negotiations in Chile. 

Metal Bulletin’s copper concentrate index fell to a multi-year low of $68.80 per tonne/6.88 cents per lb at the end of February.

What to read next
Copper in concentrate production from Ivanhoe Mines' Kamoa-Kakula complex in the Democratic Republic of Congo (DRC) fell to 61,906 tonnes in the first quarter, down by 54% from 133,120 tonnes a year earlier, with the company now evaluating local third-party concentrate purchases to advance the ramp-up of its on-site smelter, according to an April 13 production release as the market focused its attention on the impact of global sulfuric acid shortages during CESCO Week in Chile from April 13-17.
China's planned sulfuric acid export ban from May 1, historic lows for copper concentrates treatment and refining charges (TC/RCs) and a fragmenting 2026 benchmark system dominated CESCO Week 2026 in Santiago from April 13-17.
The proposal would align the index more closely with physically traded volumes in the region, and enable it to adjust to evolving market conditions. This proposal follows an observed widening of the spread between trader and smelter purchase components of the index and is aligned with a majority of market feedback. Additionally, Fastmarkets seeks feedback […]
Until now, aluminium has been hard to move, not hard to find. Global aluminium supply had remained technically intact, even as output was curtailed in parts of the Gulf, inventory buffers were drawn down or repositioned, and shipping through the Strait of Hormuz was severely disrupted.
Global aluminium producers face heightened uncertainty over power supplies, with oil and gas prices elevated by the closure of the Strait of Hormuz, through which around 20% of global oil and liquefied natural gas (LNG) flows, sources told Fastmarkets.
Fastmarkets is extending the consultation period for the methodology of several of its black mass payables indicators and prices, and is also proposing changes to the names of CIF South Korea and EWX Europe black mass prices.