Vale expects ‘completely different’ base metals division by 2020

Vale, the world’s largest producer of iron ore and nickel, believes that its base metals division will be completely different by 2020, senior executives said on Thursday October 25 during a third-quarter earnings call.

One of the principal objectives, they said, was to improve nickel operations by reducing costs and improving productivity.

VNC is the company’s nickel operation in the Melanesian country of New Caledonia, north-east of Australia. It is already undergoing a complete restructuring process, chief financial officer Luciano Siani said.

There will be further news regarding this asset soon, he added, but capacity and cost improvements must be made first.

Vale was previously willing to sell or even close VNC because of output instabilities and accumulated losses, but has now decided to revamp it before taking any further action.

The plant has capacity for 60,000 tonnes per year of nickel but output in January-September 2018 was equivalent to a run rate of only 32,270 tpy.

“This is what we’re doing before deciding whether to keep VNC in our portfolio,” Siani added.

This transformation was being done under the guidance of Eduardo Bartolomeo, who was brought back to Vale this year by chief executive officer Fabio Schvartsman to lead base metals operations, after six years pursuing other opportunities.

Bartolomeo said during the earnings call that while the changes will take some time, he expected to be leading a “brand new” division by 2020.

“We also have to adapt ourselves to the new size of our operations, which has eliminated some refineries,” Bartolomeo said. “If you think about 60,000 tonnes per year [of nickel produced by VNC] and a price of $18,000-20,000 per tonne in 2020, you will understand the opportunities.”

The benchmark three-month price for nickel on the London Metal Exchange was $12,210-12,220 per tonne on October 25. This was down by 1.41% from $12,385-12,400 per tonne on Wednesday.

Bartolomeo believed that Vale will be able to achieve its nameplate capacity for 310,000 tpy of nickel by 2021-22, but this will depend on market fundamentals.

Vale’s executives also commented during the call on Salobo 3, a new expansion to its copper mine located in Brazil.

As indicated by its name, this will be the third concentration unit at the plant. It will have capacity for 50,000 tpy for the first five years, 42,000 tpy in ten years’ time and 33,000 tpy over its whole life cycle. This means that Salobo’s lifespan will be reduced and that it will be depleted in 2052, from a previous expectation of end-of-life in 2067.

The expansion will start-up in the first half of 2022, and the investment required has been estimated at $1.1 billion.

“[Salobo 3] is a twin plant in comparison to the other two,” Bartolomeo said. “We expect a slight increase in the cash cost of Salobo because of [the early] depletion, but this should be close to what we’re seeing [for the whole complex] right now.”
 

What to read next
Copper in concentrate production from Ivanhoe Mines' Kamoa-Kakula complex in the Democratic Republic of Congo (DRC) fell to 61,906 tonnes in the first quarter, down by 54% from 133,120 tonnes a year earlier, with the company now evaluating local third-party concentrate purchases to advance the ramp-up of its on-site smelter, according to an April 13 production release as the market focused its attention on the impact of global sulfuric acid shortages during CESCO Week in Chile from April 13-17.
China's planned sulfuric acid export ban from May 1, historic lows for copper concentrates treatment and refining charges (TC/RCs) and a fragmenting 2026 benchmark system dominated CESCO Week 2026 in Santiago from April 13-17.
The proposal would align the index more closely with physically traded volumes in the region, and enable it to adjust to evolving market conditions. This proposal follows an observed widening of the spread between trader and smelter purchase components of the index and is aligned with a majority of market feedback. Additionally, Fastmarkets seeks feedback […]
Until now, aluminium has been hard to move, not hard to find. Global aluminium supply had remained technically intact, even as output was curtailed in parts of the Gulf, inventory buffers were drawn down or repositioned, and shipping through the Strait of Hormuz was severely disrupted.
Global aluminium producers face heightened uncertainty over power supplies, with oil and gas prices elevated by the closure of the Strait of Hormuz, through which around 20% of global oil and liquefied natural gas (LNG) flows, sources told Fastmarkets.
Fastmarkets is extending the consultation period for the methodology of several of its black mass payables indicators and prices, and is also proposing changes to the names of CIF South Korea and EWX Europe black mass prices.