MMG’s Las Bambas copper project on track

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

“We have been working very closely with the local community to ensure a smooth transition as families continue to relocate to the new Fuerabamba town,” ceo Andrew Michelmore said in a statement on Thursday January 15.

About 75% of families have now moved with the relocation expected to be largely complete in the first quarter of 2015, he added, saying that this has no impact on project construction.

“Construction of the Las Bambas project continued in the fourth quarter 2014 with the main activity focusing on the construction of the processing plant, primary crusher, overland conveyor and key surface infrastructure, along with the design of concentrate logistics,” the company said.

Pre-stripping activity will start in the first quarter 2015 to enable the commencement of mining in the Ferrobamba pit, MMG said

MMG has said that it expects capital expenditure to complete the Las Bambas mining complex to be in the range of $2.7 billion-$3.2 billion.

The project, which is expected to cost a total of $7 billion, is slated to eventually be one of the three biggest copper mines in the world.

In October, the company had delayed the first production at Las Bambas to first quarter of 2016 after identifying “significant risks” to the project’s schedule and capex guidance.

Shivani Singh
shivani.singh@metalbulletinasia.com
Twitter: @ShivaniSingh_MB

What to read next
To increase the transparency of our methodology, Fastmarkets clarifies that the quotation period of the MHP nickel payable indicator is the month of delivery, or the month M. Any data points Fastmarkets received otherwise will be normalized to the M month based on the monthly spreads of the prevailing exchange-traded Class-1 nickel reference price, or […]
'Probably miscalculated’ assumptions at Kakula mine force Ivanhoe to overhaul entire Kamoa-Kakula complex, explains CEO Marna Cloete.
Following an initial consultation with the market, Fastmarkets is proposing to:  The new specifications would be as follows, with amendments in italics: MB-CU-0002 Copper grade 1 cathode premium, ddp Midwest US, US cents/lb Quality: Grade A 99.9935% min copper cathode conforming to LME specifications BS EN 1978:2022 – Cu-CATH-1 or Grade 1 Electrolytic Copper Cathode ATSM B1115-10 Quantity: Min […]
Fastmarkets’ 2025 outlook for key raw materials and ingredients used in the production and distribution of fast-moving consumer goods.
Vale Base Metals plans to boost annual copper production to 700,000 tonnes by 2035, aiming to become a top-five global producer of nickel and copper. CEO Shaun Usmar highlights a focus on productivity, cost optimization and sustainable growth. With strong assets in Canada and Brazil, Vale is well-positioned to meet rising global demand.
Fastmarkets has corrected its fob Australia alumina index, which was published incorrectly on Monday June 2 and Tuesday June 3 due to a back-end calculation error. Fastmarkets has also corrected all the related inferred indices. On June 2 the following prices were published incorrectly: Fastmarkets’ MB-ALU-0002 Alumina index, fob Australia, was published in error as $375.59 per […]