Glencore cuts 2015 capex ceiling to $6bn

Glencore has cut its maximum industrial capex for 2015 to $6 billion, compared with the $6.5-6.8 billion announced in February.

Glencore has cut its maximum industrial capex for 2015 to $6 billion, compared with the $6.5-6.8 billion announced in February.

The miner’s industrial capex was $3 billion in the first six months of the year, the company said in its production report for the period.

In production guidance included in the report, Glencore set a full-year 2015 ferro-chrome production target of 1.45-1.5 million tonnes, up from 1.3 million tonnes in 2014.

Glencore’s ferro-chrome production increased 16% year-on-year in the first half of 2015 on greater output from its Lion 2 smelter.

Full-year 2015 zinc production is expected to increase to 1.52-1.57 million tonnes, up from 1.39 million tonnes in 2014.

Copper production guidance has been set at 1.5-1.55 million tonnes in 2015, roughly flat on the 1.546 million tonnes in 2014. Copper production fell 3% in the first half of 2015 as a result of lower-grade material and maintenance.

Lead production is expected to increase to 335,000-360,000 tonnes in 2015. In 2014, about 308,000 tonnes of lead was produced.

Nickel production guidance has been set at 98,000-108,000 tonnes for 2015. The company produced about 101,000 tonnes of nickel in 2014.

The table below shows the midpoint of each production guidance range against full-year production in 2014.

Glencore’s production guidance for full-year 2015, as of August 2015 

  2014                 production
Tonnes (000)      
High Low Midpoint % change
Copper 1,546 1,500 1,550 1,525 -1.36%
Zinc 1,387 1,520 1,570 1,545 11.39%
Lead 308 335 360 347.5 12.83%
Nickel 101 98 108 103 1.98%
Ferro-chrome 1,295 1,450 1,500 1,475 13.90%

Charlotte Radford 
charlotte.radford@metalbulletin.com
Twitter: @CRadford_MB 

What to read next
Fastmarkets has corrected the pricing rationale for MB-AL-0302 aluminium 6063 extrusion billet premium, ddp North Germany (Ruhr region), $/tonne, which was published incorrectly on Friday April 19. No prices were corrected.
The low-carbon aluminium differential in the US made its first move on Friday April 5 since Fastmarkets launched it five months ago.
Brazil's aluminium industry is further enhancing its sustainability by boosting renewable energy use and recycling, while mitigating risk from high-carbon imports
German copper producer Aurubis is among the least likely to consider reducing capacity despite record low treatment charges (TCs), according to its chief executive officer
European copper demand, particularly for wire rod, remains strong and seems to be outpacing broader macro-economic growth in the region, the chief executive officer of German producer Aurubis has said.
The process to place the smaller and less efficient of the two processing plants at Los Bronces on care and maintenance is expected to be completed by mid-2024 and comes as the company pushes value over volume, the chief executive officer of Anglo American Chile said