MMG’s Las Bambas copper project on track

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

“We have been working very closely with the local community to ensure a smooth transition as families continue to relocate to the new Fuerabamba town,” ceo Andrew Michelmore said in a statement on Thursday January 15.

About 75% of families have now moved with the relocation expected to be largely complete in the first quarter of 2015, he added, saying that this has no impact on project construction.

“Construction of the Las Bambas project continued in the fourth quarter 2014 with the main activity focusing on the construction of the processing plant, primary crusher, overland conveyor and key surface infrastructure, along with the design of concentrate logistics,” the company said.

Pre-stripping activity will start in the first quarter 2015 to enable the commencement of mining in the Ferrobamba pit, MMG said

MMG has said that it expects capital expenditure to complete the Las Bambas mining complex to be in the range of $2.7 billion-$3.2 billion.

The project, which is expected to cost a total of $7 billion, is slated to eventually be one of the three biggest copper mines in the world.

In October, the company had delayed the first production at Las Bambas to first quarter of 2016 after identifying “significant risks” to the project’s schedule and capex guidance.

Shivani Singh
shivani.singh@metalbulletinasia.com
Twitter: @ShivaniSingh_MB

What to read next
General Motors (GM) is investing $650 million to develop the Thacker Pass mine in Nevada, the largest known source of lithium in the US and the third largest in the world
Electrolysis processes developed by Boston Metal and Electra that eliminate the need for coal in steel production could be key to a net-zero emissions future for the metallics industry, attendees learned at Fastmarkets’ conference on January 17-19 in Dallas
US deep-sea ferrous export prices from the East Coast to Turkey have plateaued, with a Turkish mill purchasing a cargo at prices stable from the last-reported sale
Following a six-week consultation period, Fastmarkets can confirm it will amend the calculation method for all the average functions on the Fastmarkets platform from Wednesday March 1, 2023.
Consolidation, the recycling of electric vehicle batteries, US steel exports and the benefits of sustainable steelmaking were key talking points at Fastmarkets’ Scrap & Steel 2023 conference in Dallas in January
We use cookies to provide a personalized site experience.
By continuing to use & browse the site you agree to our Privacy Policy.
Proceed