MMG’s Las Bambas copper project on track

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

China Minmetals-owned MMG said its Las Bambas project in Peru was 80% complete at the end of December 2014 and it continues to expect its first copper concentrate in the first quarter of 2016.

“We have been working very closely with the local community to ensure a smooth transition as families continue to relocate to the new Fuerabamba town,” ceo Andrew Michelmore said in a statement on Thursday January 15.

About 75% of families have now moved with the relocation expected to be largely complete in the first quarter of 2015, he added, saying that this has no impact on project construction.

“Construction of the Las Bambas project continued in the fourth quarter 2014 with the main activity focusing on the construction of the processing plant, primary crusher, overland conveyor and key surface infrastructure, along with the design of concentrate logistics,” the company said.

Pre-stripping activity will start in the first quarter 2015 to enable the commencement of mining in the Ferrobamba pit, MMG said

MMG has said that it expects capital expenditure to complete the Las Bambas mining complex to be in the range of $2.7 billion-$3.2 billion.

The project, which is expected to cost a total of $7 billion, is slated to eventually be one of the three biggest copper mines in the world.

In October, the company had delayed the first production at Las Bambas to first quarter of 2016 after identifying “significant risks” to the project’s schedule and capex guidance.

Shivani Singh
shivani.singh@metalbulletinasia.com
Twitter: @ShivaniSingh_MB

What to read next
Capital is flowing back into junior mining, but selectively. Investment is increasingly favouring development‑stage assets with clearer paths to production, supported by government funding and strategic partnerships. While demand for critical minerals underpins the cycle, early‑stage explorers continue to struggle for capital as investors prioritise discipline, ESG alignment and near‑term cash flow.
Copper in concentrate production from Ivanhoe Mines' Kamoa-Kakula complex in the Democratic Republic of Congo (DRC) fell to 61,906 tonnes in the first quarter, down by 54% from 133,120 tonnes a year earlier, with the company now evaluating local third-party concentrate purchases to advance the ramp-up of its on-site smelter, according to an April 13 production release as the market focused its attention on the impact of global sulfuric acid shortages during CESCO Week in Chile from April 13-17.
China's planned sulfuric acid export ban from May 1, historic lows for copper concentrates treatment and refining charges (TC/RCs) and a fragmenting 2026 benchmark system dominated CESCO Week 2026 in Santiago from April 13-17.
The proposal would align the index more closely with physically traded volumes in the region, and enable it to adjust to evolving market conditions. This proposal follows an observed widening of the spread between trader and smelter purchase components of the index and is aligned with a majority of market feedback. Additionally, Fastmarkets seeks feedback […]
Until now, aluminium has been hard to move, not hard to find. Global aluminium supply had remained technically intact, even as output was curtailed in parts of the Gulf, inventory buffers were drawn down or repositioned, and shipping through the Strait of Hormuz was severely disrupted.
Global aluminium producers face heightened uncertainty over power supplies, with oil and gas prices elevated by the closure of the Strait of Hormuz, through which around 20% of global oil and liquefied natural gas (LNG) flows, sources told Fastmarkets.