Siemens VAI leads consortium to supply $360m steelmaking plant in India

Siemens VAI Metals has won an order worth €290 million ($359 million) as part of a consortium to supply a steelmaking plant for India’s National Mineral Development Corp (NDMC), the Austrian technology company said on Monday August 6.

Paragraph entered by Atlantic migration, in order for SteelFirst articles to display correctly on Metal Bulletin.

The plant, to be built at Nagarnar in Chhattisgarh state, is part of a $3 billion project that will see the steelmaking company producing hot rolled coil (HRC) by 2014-15. The project is scheduled for completion by mid-2015.

Plantmaker Siemens will be responsible for the design and supply of two basic oxygen converters, two 175-tonne desulphurisation plants, two ladle furnaces and a degassing plant.

Siemens will also be in charge of the material handling and de-dusting systems, and plants for gas recovery and water treatment.

When finished, the complete integrated production complex is intended to have an annual output capacity of 3 million tpy of steel.

The Indian branch of Siemens VAI Metals will be executing the project with consortium members SEW Infrastructure and Mukand Engineers, which will look after the manufacturing and erection of the steel structures and the general equipment.

The plant will comply with environmental standards in both Europe and India, Siemens added.

What to read next
The attack by the Russian army on a hydroelectric power plant in Nova Kakhovka in southern Ukraine on Tuesday June 6 has affected steelmaking operations at Kryvyi Rih, where ArcelorMittal’s Ukrainian steel mill and Metinvest’s mining and processing plants (GOKs) are located, sources have told Fastmarkets
Fastmarkets will launches its price assessment for ferro-chrome low carbon, 0.10% C, basis 60-64.9% Cr, CIF Europe, on Tuesday June 6.
Find out how Mitsui and Kobe Steel seek to reinforce their position in direct-reduced iron (DRI) production in the Middle East with the construction of a low-CO2 iron metallics production plant.
Fastmarkets proposes to launch published netback rates for both purity and incoterm differentials for its aluminium P1020A Rotterdam premiums.
Fastmarkets proposes to amend the publishing frequency of its three calcined alumina prices from monthly to quarterly.
Fastmarkets invited feedback from the industry on the pricing methodology for cobalt hydroxide, min 30% Co, inferred, China, $lb, via an open consultation process between May 4 and June 1, 2023. This consultation was done as part of our published annual methodology review process.